Sunday, August 8, 2010

Male Scorpio Disappeared

Ready for the floor & concrete

First the good news: the floor is laid throughout the house and all the preparations for the flooring were getrofen. According to the plan come tomorrow. However, delaying the power connector (why I do not know, vacation time or missing your electrical meter at the Eon are the possible reasons), why must dry the floor at the beginning without heating. According to our site manager at the weather no problem.

look at the scenes as the air supply disappears into the floor insulation

living room / kitchen, look in the hallway

Art in: hoses, outgoing from the heating circuit

panel of the heating of whom stolen? ;-)

Unfortunately, there is another problem: the Hausanschlussäule by Eon was set flush against the wall. This has challenged our construction manager because the house is of course still plastered. So far so good, my cunning plan, auszubuddeln the column itself and easy to move by 10 cm, is magnificently clever: Our civil contractors have - without asking us or learn - the cast in the column bases ...

Now we have serious intentions to leave the house plastered around the column. Anything else would probably lead to further cost or at least a delay, because the base would be braces. We open a bottle of champagne when the chapter is earth and deep work finally finished. The work and our Contractors can not be calculated and take our last nerve.

column in concrete. Here, nothing moves more

connecting pillar set flush to recognize
too. The last piece of downpipe is slightly askew,
was because the rain water pipes too close to the wall set
. Cosmetic, but annoying.